NSU Facilities Manager Monte Mehlhoff has issued a regional sports complex construction update.
Barnett Area
- Steel erection is complete
- Second floor concrete is poured
- Underground plumbing is underway on first floor
- Exterior steel stud framing has started
Football Area
- Steel erection continues
- Underground plumbing and electrical is in progress on service level
- Lower bowl seating is being cast
- East retaining wall is in progress
- Scoreboard foundations are being installed
Softball Area
- Preload berm is being removed to start foundations