NSU Facilities Manager Monte Mehlhoff's Regional Science Center construction update outlines activity inside and outside the building.
In the south wing:
- Plumbers continue with overhead piping on both levels
- Electricians are installing piping
- On both levels, workers are assembling and installing HVAC ductwork and installing fire sprinkler piping and sheetrock/taping
Elsewhere:
- Workers are framing walls on the second floor of the north wing
- The spray foam contractor is installing membrane on the east side
- Masons continue to lay brick on the west side
- Carpenters are working on in-wall backing
- Workers have begun installing window frames on the east side