Submitted by admin on
Image

NSU Facilities Manager Monte Mehlhoff's Regional Science Center construction update outlines activity inside and outside the building.

In the south wing:

  • Plumbers continue with overhead piping on both levels
  • Electricians are installing piping
  • On both levels, workers are assembling and installing HVAC ductwork and installing fire sprinkler piping and sheetrock/taping

Elsewhere:

  • Workers are framing walls on the second floor of the north wing
  • The spray foam contractor is installing membrane on the east side
  • Masons continue to lay brick on the west side
  • Carpenters are working on in-wall backing
  • Workers have begun installing window frames on the east side