NSU Facilities Manager Monte Mehlhoff has issued a campus construction update.

Regional Science Education Center

Plumbers and electricians continue with rough-ins and HVAC workers are assembling and installing ductwork on both levels of the south wing.

Workers are hanging sheetrock on the first floor of the south wing and taping on the second floor of the south wing. 

The spray foam contractor is installing transition membrane on the west side of the building.

Carpenters continue with window blocking on the exterior and in-wall backing on the interior. A window for testing has been installed.