NSU Facilities Manager Monte Mehlhoff has issued the latest update on construction at the Jewett Regional Science Education Center.

In the south wing, plumbers are installing overhead piping. The HVAC contractor continues to assemble and install ductwork and the sprinkler contractor to install piping. Drywall taping is under way on the second floor.

Electricians are working on main power and campus loop power.

Framing continues in the north wing. The spray foam contractor is installing transition membrane and applying spray foam on the west side of the building. Masons are laying brick on the building's west side, and carpenters continue with wood blocking and backing.