NSU Facilities Manager Monte Mehlhoff has issued a campus construction update.
Regional Sports Complex
- Continued pouring concrete walls and footings at football stadium
- Dahme continued working on utilities
- Ground improvements completed on Barnett Addition
- Dug and poured west footings for Barnett Addition
Science Center South Parking Lot
- Gravel and asphalt work under way
- Estimated completion by late June
JFAC Roof
- Roof replacement should be complete by Monday, June 8