NSU Facilities Manager Monte Mehlhoff has issued a campus construction update, in which much work shifts to the north end of the Regional Science Center.

Regional Science Center

North Wing

  • Masons are laying brick on the west wall
  • Windows are being installed on the south side
  • Spray foam is being applied to the north wall
  • Wall framing and work on the lobby stairs continues
  • Drywallers are hanging sheetrock on both levels
  • Second-floor ductwork is being installed


South Wing

  • First-floor polishing is under way
  • Tapers are working in second-floor east corridor and pods
  • Plumbers are doing rough-ins on first-floor restrooms, running heating mains and hooking up VAVs
  • Ductwork installation and VAV work continues on both levels
  • Controls work is ongoing


Site-wide

  • Refrigeration line installation
  • Pipe  and duct insulating
  • The chiller has been placed on the pad in the mechanical yard
  • Electricians continue with rough-ins in the north wing, pulling wire to panels, and piping for lights on second floor south


Krikac and north campus pillars

Work is set to begin May 15.