NSU Facilities Manager Monte Mehlhoff's Regional Sports Complex construction update again includes photos.
Image1 - North stair tower curtain wall mullions is installed, with glazing to follow.
Image 2 - Newly installed Dacotah Bank Stadium signage and "N" logo signage is shown on west (home) grandstand.
Barnett Center Addition
• Painting is completed at second-level Barnett Center spaces.
• Tile and fixtures have been installed in the restrooms; bathroom partitions are on site.
• HVAC/plumbing/electrical equipment is being installed in mechanical rooms.
• Ceiling and A/V install has begun at second-level event space.
• Electrical and HVAC rough-in work is nearing completion on first floor.
• Drywall is hung on first level football locker rooms; mudding and taping is complete and priming and painting have begun.
• Locker fabrication will begin in April and be installed June 12.
• KONE is on site, and plans to complete both Barnett Center elevators by the end of March. East (passenger) elevator is installed. West (service) elevator installation has begun.
• Metal Lux wall panels have been installed at both the east and west decks at the Barnett Center Addition.
• Bridge connecting the BC Addition and FB Stadium arrives on site and will be installed on March 23.
FB Stadium
• Spray foam insulation on the interior side of all exterior walls is complete.
• Fifth level walls have been primed and painted.
• Electrical, mechanical, plumbing and fire sprinkler rough-ins are complete on fourth level.
• Fourth level suites and all commons spaces are all dry-walled/taped/mudded and priming/painting is wrapping up.
• Fourth level bar/lounge has all glazing installed at exterior curtain walls.
• Interior casework for fourth level suites is being installed.
• Third level loge – Interior restrooms, concessions, and back of house areas are framed in and M.E.P. rough-in work is nearing completion. Drywall will follow.
• Third level loge – Ceiling framing at loge concourse is complete. Metal panel ceilings will be installed upon arrival in April.
• M.E.P. rough-in work continues on second-level bathrooms and concessions.
• Mason continues to lay block interior CMU walls at restrooms and concessions on second level concourse.
• Mason continues installation of CMU block walls on first level service areas, mechanical rooms, etc.
FB Field
• All drainage, subgrade construction, and field curb has all been installed. Now we wait until spring for top layer fine grade and turf roll-out/install. Tentatively shooting for April 1 to begin site work pending weather/frost.
• Work continued on the metal panel installation. East, north and south elevations are complete, and install crew is about 90 percent finished with metal panels on the west grandstand façade.
• Upper EPDM roof system is complete. Metal parapet cap remains.
• Second level concourse EPDM roof system is complete. Metal parapet cap remains.
• Daktronics Scoreboard (50’ tall x 80’ wide) has been erected. Metal cladding will be wrapped around back side and columns between April 14 and 22.
• Construction on the ticket booth structural steel and roof decking is complete and interior wall framing has begun.
• Southern Bleacher has installed north additional seating alternate, and the south additional seating alternate will be installed at the end of March when materials arrive.
• The upper chairback seats (300 level) arrive and will begin installation next week
• The Dacotah Bank Stadium and Northern “N” signs were installed on the east grandstand façade.
• Football stadium Musco light poles and fixtures were erected, and stadium is installed. Final aiming of fixtures will be completed at a later date.
Softball Stadium
• Concrete contractors have finished the lower bowl seating pours, and have poured dugouts and dugouts roofs.
• All concrete field walls and bullpen areas have been poured and are complete.
• Steel structure for the softball press box and suite has been erected and moment connection testing has passed.
• All underground M.E.P rough-ins are installed at softball concessions/Restroom and the concrete floor slab has been poured.
• Softball field subgrade drainage and field curb construction will take place in the spring.
• CMU block at the softball restroom and concessions structure will begin by the end of the month / April 1 depending on weather.
• Framing of softball press/suite has begun.