Facilities Manager Monte Mehlhoff has issued a campus construction update.

Regional Science Center

South Wing

  • Floor polishing continues on the second floor corridor
  • Painters are working on both levels


North Wing

  • Masons continue to lay brick
  • Glass is being installed in the windows on the south side
  • Transition membrane and spray foam application continue
  • Exterior metal wall panels are being installed on the east side of the building
  • Drywallers are sheetrocking second-floor restrooms


Throughout the Building

  • Tapers are working in the corridors on first and second floors south and taping on both levels of the north wing
  • Plumbers are doing rough-ins in the first-floor restrooms, hooking up VAVs and running heating lines
  • The HVAC contractor continues installing ductwork on both levels of the south wing and on second floor north
  • Pipe and duct insulators continue to work in various areas of the building
  • Electricians are building rough-ins at the north wing, pulling wire  and installing piping for lights
  • The controls contractors are building rough-ins in various areas of the building

Krikac and north campus pillars

Work is set to begin May 15.