NSU Facilities Manager Monte Mehlhoff has issued a science center construction summary as part of this week's campus construction update.

Regional Science Center

Executive Construction Summary

Ongoing work in the south wing:

  • First-floor polishing
  • Window and first-floor interior "storefront" installation
  • First-floor restroom rough-ins
  • First-floor heating main and VAV installation
  • Pipe insulation
  • Electrical wire pulling
  • HVAC ductwork and VAV installation on both floors
  • Painting
  • Controls rough-ins

Ongoing work in the north wing:

  • Spray foam installation
  • Bricklaying on the south and west walls
  • Wall framing on both floors
  • Sheetrock hanging on second-floor pods and north wing
  • First-floor restroom rough-ins
  • First-floor electrical rough-ins
  • HVAC ductwork and VAV installation on second floor
  • Controls rough-ins

Exterior:
Workers have begun installing exterior metal wall panels on the
west side.

Krikac and north campus pillars
Work is set to begin May 15.