​NSU Facilities Manager Monte Mehlhoff has issued a campus construction update.

Sports Complex

  • Continued soil correction in the softball area
  •  Dug area C football for footings and foundation walls and poured footings
  • Continued soil corrections for Area B football stadium
  • Storm sewer tied in

Misc.

  • Dirt work being done for new parking lot south of Science Center
  • Barnett Center track being resurfaced
  • Barnett Center and Heating Plant new fire alarm systems are installed and functioning

JFAC
New roof installation in progress

Roof Installation Progress Report

McWelsh
New roof slated for July