NSU Facilities Manager Monte Mehlhoff has issued a campus construction update.

Sports Complex

  • Monday's 2 1/2 inches of rain delayed ground improvements for three days
  • Storm sewer under Barnett Addition was removed and old roof drain tied to new 90-inch storm sewer
  • Layout for footing excavation performed on south half of football stadium


JFAC
New roof installation in progress

McWelsh
New roof slated for July