NSU Facilities Manager Monte Mehlhoff has issued a Regional Sports Complex construction update.
See construction live-streamed at Campus Construction Live Video.
Barnett Center Area
- Interior framing continues, 90 percent complete
- MEP trades are doing roughing in
- Window install is in progress
- Metal panels in progress
- EPDM roof is complete
Football Area
- Framing and sheeting in progress
- Concrete 90 percent complete
- Plumbers are roughing in
- Steel erector is doing detail work
- Field install has started
- Mason starts on Monday
Softball Area
- Footings and foundation walls continue