NSU Facilities Manager Monte Mehlhoff has issued a construction update.

 

Barnett Center area

  • Interior and exterior framing continue
  • Pouring main level floor 50 percent complete
  • All trades are roughing in walls
  • EPDM roofing has started

 

Football Area

  • Decking and detailing continue for steel erector
  • All trades roughing in
  • Concrete pours continue on floors and lower bowl seating
  • Crane will be leaving Monday, Sept. 28 

 

Softball Area

  • Digging for footing and foundation walls