​NSU Facilities Manager Monte Mehlhoff's construction update details progress on the NSU Regional Sports Complex.

Football Area

  • Steel erection continues on stadium
  • Landscape walls that create the football field and berms are in progess
  • Started pouring floors on steel decking
  • MEP trades are roughing in floor penetrations
  • Installing GEO foam


Softball Area

  • Started digging footings for grandstand


Barnett Addition

  • Interior and exterior steel stud framing inprogess
  • MEP rough-in, main floor
  • Doing mock-up for commissioning agent to inspect